Japan to Simplify Environmental Assessments for Power Plant Repowering from April 2027

Oct 29
4 min read

Japan will introduce a simplified initial environmental impact assessment (EIA) procedure for certain power plant replacement projects on 1 April 2027.


Under the current framework, developers replacing existing power plants generally face the same preliminary environmental assessment requirements as developers constructing new facilities, including the examination of alternative project locations and potential environmental impacts.


The reform allows qualifying replacement projects to focus their initial assessment on the proposed replacement and environmental information from the existing facility, rather than repeating the ordinary preliminary assessment of alternative locations.


On 9 October 2026, the Cabinet approved implementing orders establishing the eligibility criteria and commencement date under the 2025 amendment to the Environmental Impact Assessment Act (Act No. 73 of 2025).


The reform is particularly relevant to investors and developers considering the repowering of existing thermal, geothermal and wind power plants in Japan.


What changes in the environmental assessment procedure?


Japan's Environmental Impact Assessment Act (環境影響評価法) requires certain large-scale projects to assess their potential environmental impacts before implementation.


For Type 1 projects (第一種事業), the procedure includes a mandatory planning-stage environmental consideration document (hairyosho, 配慮書).


Type 2 projects (第二種事業) are screened to determine whether a full EIA is required, and preparation of a planning-stage document is optional.


Under the ordinary procedure, developers must describe the proposed project area and its surroundings and provide preliminary environmental survey, prediction and evaluation results. This generally involves considering alternative project locations and scales.


For qualifying Type 1 replacement projects, the amended Act introduces a specific replacement planning-stage document (tatekae hairyosho, 建替配慮書).

Under Article 3-3(2), two items replace the ordinary requirements concerning the surrounding area and preliminary environmental assessment results:

  1. The proposed replacement project area.

  2. The details of the environmental considerations for the replacement project.


This approach allows developers to draw on existing environmental information, including monitoring results and previous assessments, when considering the impacts of the replacement facility.


The replacement document remains mandatory for qualifying Type 1 projects, and the Minister of the Environment retains the power to provide opinions concerning environmental protection.


Which power plant replacement projects qualify?


The new procedure applies to qualifying projects involving thermal, geothermal and wind power plants.


The existing facility must be removed or its use discontinued and replaced by a facility of the same type within prescribed geographical and output limits.


Under Article 7-2 of the Environmental Impact Assessment Act Enforcement Order, the following criteria apply:

Power plant type

Maximum distance

Maximum ratio of new to existing output

Thermal

300 metres

2.0

Geothermal

300 metres

1.3

Wind

300 metres

1.1

For example, replacing an existing 100 MW wind farm with a 110 MW facility could satisfy the output criterion, provided the geographical and other statutory conditions are also met.


The 300-metre distance is measured from the boundary of the area where the existing facility is installed.


The Ministry of the Environment's technical committee has proposed using the existing plant site for thermal projects, the generating equipment site for geothermal projects and turbine installation positions for wind projects. These interpretations remain subject to final administrative guidance.


No equivalent replacement criteria have been established for solar or hydroelectric power plants. Upgrading or refurbishing an existing facility while continuing to use it also falls outside this replacement framework.


Do the other EIA requirements still apply?


Yes. The reform simplifies the initial planning-stage document but does not remove subsequent environmental assessment obligations.

Developers must still complete the applicable procedures, including:

  • Scoping document (hōhōsho, 方法書): Identifies the environmental impacts to be studied and the assessment methods.

  • Draft assessment (junbisho, 準備書): Presents environmental assessment results and proposed mitigation measures.

  • Final assessment report (hyōkasho, 評価書): Finalises the assessment following the applicable review procedures.

  • Post-project reporting (hōkokusho, 報告書): Reports relevant environmental impacts after implementation, where required.


The amended legislation also adjusts the required contents of the scoping document to reflect the environmental considerations identified in the replacement planning-stage document.


For power generation projects, the EIA process operates under both the Environmental Impact Assessment Act and the special provisions of the Electricity Business Act. The Ministry of Economy, Trade and Industry (METI) is the competent minister for the planning-stage document.


Separate electricity-related authorisations, construction plan procedures and other applicable approvals remain unaffected.


Effective date and transitional provisions


The new procedure takes effect on 1 April 2027. Under Article 2 of the Supplementary Provisions to Act No. 73 of 2025, the previous rules continue to apply to certain ongoing EIA procedures where the prescribed planning-stage document and its summary, or the scoping document and its summary, have already been sent before commencement.


For power generation projects already at the scoping stage, the application of these transitional provisions should be examined alongside the relevant Electricity Business Act procedures. Further transitional measures may also be established by Cabinet Order.


For further information on electricity-related regulatory requirements and market-entry procedures, see our Energy Business in Japan service page.

Official Japanese sources

Regulatory information as of 29 October 2026.